Location
York, NY
Owner
Livingston County
Engineer
Ravi Engineering
Project Manager
Brandon Freeman
Contract Value
$609,885
Description
The work will include, but not be limited to, removal of the existing steel girder superstructure and replacement with Tappan Zee concrete bridge panels founded on integral abutments on piles. The existing abutments will be cut down but
remain in place, and the proposed abutments will be built behind them. Medium stone fill will be placed in the vicinity of the new bridge abutments. There will be full-depth pavement reconstruction extending approximately 230 feet within
the limits of the project along with a pipe extension on the east side of the structure.